BEALE AFB |
TITAN I MISSILE BASE CONSTRUCTION 851st STRATEGIC MISSILE SQUADRON BEALE AFB MARYSVILLE, CALIFORNIA
UNITED STATES ARMY CORPS OF ENGINEERS CONSTRUCTION HISTORY PHOTOS AERIAL SITE 1A LINCOLN
AERIAL SITE 1A LINCOLN
SITE 1A LINCOLN
LAUNCHER #1 AERIAL SITE 1A LINCOLN
ANTENNA SILOS AERIAL SITE 2A LIVE OAK / SUTTER BUTTES
POWER HOUSE AERIAL SITE 2A LIVE OAK / SUTTER BUTTES
AERIAL SITE 1C CHICO
INSTRUMENTATION
MISSILE PLACEMENT
IN THE NEAR FUTURE I HOPE TO ACQUIRE ORIGINAL COPIES
EXCAVATION OF LAUNCHER #1 LINCOLN
TUNNEL EXCAVATION SITE 1C
EXCAVATION OF LAUNCHER #1 SITE 1A
OPEN CUT EXCAVATION SITE 1B TAKEN MARCH 1, 1960
OPEN CUT EXCAVATION LAUNCHER #2 SITE 1C
REMOVING ROCK FROM POWERHOUSE AREA SITE 1A
EARTH SLIDE NEAR LAUNCHER #2 SITE 1A
OPEN CUT EXCAVATION LAUNCHER #2 TAKEN IN MARCH 1960 SITE 1A
ANTENNA SILOS OPEN CUT EXCAVATION SHORING OF SLOPE SITE 1A
OPEN CUT EXCAVATION OF POWERHOUSE AND CONTROL CENTER SITE 1C
SHAFTING OPERATION EQUIPMENT LAUNCHER #1 SITE 1A
ROCK BOLT DRILLING SITE 1A
SHAFTING OPERATIONS SHOWING STEEL RING BEAMS AND APPLYING GUNITE LAUNCHER #1 SITE 1A
LINER PLATE LAUNCHER #2 SITE 1A
ROCK BOLTS SEEN UNDER CONTROL CENTER SITE 1A
ROCK BOLTS BEING PLACED UNDER CONTROL CENTER SITE 1A
ROCK BOLTS CLOSE UP UNDER CONTROL CENTER SITE 1A
ROCK BOLTS SITE 1A
BUCKLED LINER PLATE INSIDE LAUNCHER SITE 1A
COMPACTING BACKFILL AROUND ANTENNA SILOS SITE 1A
BACKFILLING SITE C
TUNNEL BACKFILL BETWEEN JUNCTION 10 AND ANTENNA TERMINAL SITE 1A
TUNNEL BACKFILLING SITE 1A
CONCRETE BATCH PLANT SITE 1A
CONCRETE PLACEMENT MISSILE SILO NUMBER 2 SITE 1A
SETTING FORMS FOR ANTENNA SILOS SITE 1C
FORMING PROPELLANT TERMINAL SITE 1C
FORMING MISSILE SILO NUMBER 2 SITE 1A
FORMING EQUIPMENT TERMINAL WALL SITE 1A
FORMING MISSILE SILO TOP SLAB SITE 1A
MOVABLE STEEL FORMS SURROUND THE CONTROL CENTER SITE 1A
MOVABLE STEEL FORMS BEGIN TO TAKE SHAPE FOR CONTROL CENTER SITE 1A
MOVABLE STEEL FORMS BEGIN THE POWERHOUSE SITE 1A
SLIP FORMS BEING PLACED IN MISSILE SILO #1 SITE 1A
SLIP FORMS BEING PLACED IN MISSILE SILO #1 SITE 1A
SLIP FORMS BEING PLACED IN MISSILE SILO #1 NOTICE THE BUGGIE, HOPPER AND HOIST BUCKET SITE 1A
CONCRETE WALL FINISHING MISSILE SILO #1 SITE 1A
REINFORCEMENT STEEL MISSILE SILO #1 NOTICE LOX HEATING AND VENTILATING TUNNEL OPENINGS SITE 1A
REINFORCEMENT STEEL FOR AIR EXHAUST SITE 1A
REINFORCEMENT STEEL ANTENNA SILOS SITE 1A
REINFORCEMENT STEEL FOR FOUNDATION OF LIQUID OXYGEN TANK SITE 1C
LIQUID OXYGEN FUEL CRIB FOR MISSILE SILO #1 SITE 1B
SPRING BEAMS IN POWERHOUSE SITE 1C
SPRING BEAMS FOR POWERHOUSE GENERATOR SLAB SITE 1A
SPRING BEAMS FOR CONTROL CENTER SITE 1C
COIL SPRING MOUNTS FOR PROPELLANT TERMINAL SITE 1A
SPRING BEAMS IN EQUIPMENT TERMINAL #1 SITE 1A
PROPELLANT TERMINAL LOOKING INTO INTERCONNECTING TUNNEL NOTICE SEALED PIPE ENDS AND PURGE SET UP
LOX CRIB MISSILE SILO AT INTERCONNECTING TUNNEL LEVEL. NOTICE INTERIM PIPING INSTALLATION
LOX CRIB IN THE MISSILE SILO. NOTICE THE CATCH POT INSTALLATION
FUEL CRIB IN MISSILE SILO RP-1 FLOW CONTROLLER AND AIR RELEASE TANK INSTALLATION
TUNNEL JUNCTION 12 FUEL TRANSFER PANEL
TUNNEL JUNCTION 12 FUEL CONTROL VALVES AND PIPING INSTALLATION
INTERCONNECTING TUNNEL NOTICE FIELD INSTALLATION SET-UP
COMPLETED INTERCONNECTING TUNNEL INSTALLATION
PROPELLANT TERMINAL MAIN DECK PIPING INSTALLATION FOR LOX TANK SAFETY VALVE MANIFOLD
PROPELLANT TERMINAL MAIN DECK VALVES AND CONNECTIONS TAPED FOR LEAK CHECK DURING TESTING
PROPELLANT TERMINAL MAIN DECK COMPLETED INSTALLATION OF LOX TANK SAFETY VALVE MANIFOLD NOTICE TRANSFER PANELS IN BACKGROUND
PROPELLANT TERMINAL MAIN DECK INTERIM LOX CONTROL VALVE INSTALLATION
PROPELLANT TERMINAL MAIN DECK COMPLETED VALVE INSTALLATION AND TRANSFER PANELS
PROPELLANT TERMINAL LOWER LEVEL FLEX HOSE AND PIPE SUPPORT INSTALLATION
PROPELLANT TERMINAL HIGH PRESSURE GASEOUS BOTTLE CLUSTER AND CONTROL MANIFOLD
RADIATION SHIELD BETWEEN VENT SHAFT AND INTERCONNECTING TUNNEL
PROPELLANT LOADING SYSTEM TESTING EQUIPMENT HIGH PRESSURE RECHARGER AND LIQUID NITROGEN STORAGE TANK
|
Copyrighted © 1996-2007 The Housing Group, Inc. All Rights Reserved. |